本帖最后由 wyatt 于 2014-11-18 09:58 编辑
开个贴记录一下建房的路程
看了几个月的房子,转战lower/upper north shore, st ives, west pennant hills... 始终找不到自己满意的,当然也是budget有限.
后来发现身边的朋友都在盖房子,虽然省不到钱,但至少房型可以选个自己喜欢的,也是个不错的选择.于是我们一边留意我们的dream house,一边寻找推倒重盖的地.终于,有一天机会来了,地挺平,挺方正,有700平,walk distance to school and train station,符合我们的大部分需求,果断拿下,从此义无反顾的开始了建房之路.
对了,大家要多鼓励多支持呀..我的意思,你懂的..
-----------------------------------------------------------------------------------------------------------------------------
01/12/13 - Deposit with M and C
09/12/13 - Old House Settlement
13/01/14 - Tender Appointment with M and C
20/01/14 - Tree Remove Application to Council
21/01/14 - Accept Tender (M)
21/01/14 - Give notice to tenant
07/02/14 - Council Approved for Tree Removal
12/02/14 - Contract Appointment and External color selection
12/02/14 - Sign the CONTRACT (M)
19/02/14 - 5% Deposit
27/02/14 - Contract Variation 1
28/02/14 - Section 149 Application to Council
04/03/14 - Section 149 Received
27/03/14 - Confirm Demolition with Democorp
27/03/14 - Start CDC process for Demolition
09/04/14 - Internal color selection and electrical appointment
11/04/14 - CDC preparation completed (5 weeks)
13/04/14 - Tenant moved out
14/04/14 - Requested gas meter removal (Energy Australia)
15/04/14 - Tree Removal & CDC lodged
16/04/14 - Demolition CDC Approved
17/04/14 - Gas meter removed (3 days)
23/04/14 - BASIX variation
24/04/14 - Color variation 1
05/05/14 - Give demolition notification to neighbours and council (At least 5 working days before start)
05/05/14 - Color variation 2
08/05/14 - CDC Approved
12/05/14 - Color Quote and Schedule Signed
14/05/14 - Demolition (5 days)
15/05/14 - Color Variation Signed/ Final Drawing Started
30/05/14 - Final Drawing completed
10/06/14 - Site/Construction Start
19/06/14 - Slab Completed
11/07/14 - Frame Completed
19/07/14 - Tile Selection Appointment (Di Lorenzo)
23/07/14 - Brickwork Start
14/08/14 - Roof Tile Completed for first floor
04/09/14 - Tile Selection Finalized
10/09/14 - Brickwork Completed
29/09/14 - Roof Tile Completed for ground floor
29/09/14 - Electrical Rough In Completed
03/10/14 - Gyprock Start
09/10/14 - Gyprock Completed
10/10/14 - Lock Up Stage Completed
16/10/14 - Fixing Stage Completed
17/10/14 - Final Stage Started
27/10/14 - Wet Area Tiling Started
15/11/14 - Wet Area Tiling Completed
17/11/14 - Painting Completed
-----------------------------------------------------------------------------------------------------------------------------
Wisdom Estimation - Manhattan 44
Manhattan 44 - Upgrade price
Eden Brae - Cremorne 41 price
Metricon Nolan 41 Pre Tender Estimation
Metricon Nolan 41 Kingston vs. Chateau
Metricon Variation Price
Sherwood 42 Pre Tender Estimation
Clarendon Color Studio - 多图
Allcastle Palace Regent 12 Variation price
DAIKIN Capacity
ActronAir Capacity
Sarking to roof and walls
Demo注意事项
Brick Mortar Types
TFO
M Tender Appointment
M Floor Covering Price
Brick Selection
M Sound Proof between Floors Price
Demolition Quote - Home Force
Things Included in Demolition Quote
Demolition Quote - Democorp
Demolition Quote - City Civil
Contract Appointment
External Color Selection
Gas Meter Removal
Color Selection
Electrical Selection
Color Quote 1
Color Quote 2
Color Selection Process
All About Demolition
Final Drawing
Construction Forecast
Week 1
Week 2
Week 3
Week 4
Week 5
Week 6
Tile Selection
Week 7
Week 8
Week 9
Week 10
Week 11
Week 12
Week 13
Week 14
Week 15
Week 16
有关铺网线
Week 17
Week 21
Week 22
Week 23
-----------------------------------------------------------------------------------------------------------------------------
Total working days - 102
Rain delays - 11 Days
Public Holiday - 2 Days |